Construction of Phase One and associated infrastructure including sports fields, roads, and landscaping.
Scope of Work:
- Earthworks and backfilling totalling 250,000 m³.
- 25,000 m² of asphalt works including base layers.
- Electrical works including 30,000 linear meters of cables and supply & installation of 42 high-mast lighting poles (12 m and 16 m) with individual control systems.
- 15,000 m² of interlock roads and walkways.
- Drainage and water supply networks.
- Supply and casting of over 1,000 m³ of reinforced concrete for fences, column foundations, and related works.
Sports Facilities Constructed:
- Five-a-side football pitch (artificial turf)
- Regulation football field (natural grass)
- International-standard running track
- 4 Handball courts (Tartan)
- 4 Volleyball courts (Tartan)
- 2 Tennis courts (Tartan)
- 4 Basketball courts (Tartan)